Critical Path MCQ Quiz - Objective Question with Answer for Critical Path - Download Free PDF

Last updated on Apr 13, 2025

Latest Critical Path MCQ Objective Questions

Critical Path Question 1:

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. 3
  2. 9
  3. 81
  4. 27

Answer (Detailed Solution Below)

Option 2 : 9

Critical Path Question 1 Detailed Solution

Concept:

In CPM:

The standard deviation of critical path:

σcp Sumofvariancealongcriticalpath

σcpσ12+σ22++σ82+σ92

Where, σ1, σ2, ...., σ8, σ9 are the standard deviation of each activity on the critical path   

Calculation:

Given:

σ1, σ2, ...., σ8, σ9 = 3

σcp = σ12+σ22++σ82+σ92

σcp32+32+32+32+32+32+32+32+32

σcp9×9 = 9

∴ the standard deviation of the critical path is 9.

Critical Path Question 2:

Which of the following statements is NOT true about critical path method (CPM)? 

  1. CPM is concerned with activities.
  2. CPM is suitable for non - repetitive projects.
  3. CPM cannot be analysed statistically.
  4. CPM establishes a relationship between time and cost.

Answer (Detailed Solution Below)

Option 2 : CPM is suitable for non - repetitive projects.

Critical Path Question 2 Detailed Solution

Concept: 

Critical Path Method (CPM):

  • CPM is best suited for repetitive and predictable projects, like construction, maintenance, manufacturing, etc. It assumes known and fixed time estimates, which is not ideal for non-repetitive or highly uncertain projects.
  • CPM uses deterministic time estimates (i.e., fixed durations), so it doesn't involve statistical analysis like PERT (which uses probabilistic time estimates).
  • CPM helps in time-cost optimization, allowing for crashing of activities to reduce project duration at additional cost.

 

Program (Project) Evaluation and Review Technique (PERT):
  • Program Evaluation and Review Technique (PERT) is a method used to examine the tasks in a schedule and determine a Critical Path Method variation (CPM). It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project.
  • It estimates the shortest possible time each activity will take, the most likely length of time, and the longest time that might be taken if the activity takes longer than expected.  The US Navy developed the method in 1957 on the Polaris nuclear submarine project.

Additional Information

Difference between PERT and CPM

PERT

CPM

Project Evaluation and Review Technique

Critical Path Method

It is event-oriented.

It is activity-oriented.

It is associated with probabilistic activities.

It is associated with deterministic activities.

It is based upon a three-time estimate to complete an activity.

te=(to+4tm+tp6)

Where, te = expected time to complete an activity

to  = optimistic time, tm = mean time, t = pessimistic time

It is based upon a single time estimate to complete an activity.

It usually doesn’t consider cost analysis.

It gives importance to cost analysis & crashing is done to minimize the cost of the CPM project.

Applications: Mainly used for R & D project

Applications: Mainly used for Construction project

Critical Path Question 3:

The critical activity has:

  1. Normal float
  2. Maximum float
  3. Minimum float
  4. Zero float
  5. None of these

Answer (Detailed Solution Below)

Option 4 : Zero float

Critical Path Question 3 Detailed Solution

The activities with zero slack of head event and zero slack for the tail event, are called as critical activities.

 The activities with zero float are called critical activities. The sequence of critical activities in a network is called the critical path.

So, the critical path, by definition, has a zero total float or delay. And the delay of one activity prolongs the duration of completion of the project.

Critical Path Question 4:

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. 3
  2. 9
  3. 81
  4. 27
  5. 54

Answer (Detailed Solution Below)

Option 2 : 9

Critical Path Question 4 Detailed Solution

Concept:

In CPM:

The standard deviation of critical path:

σcp Sumofvariancealongcriticalpath

σcpσ12+σ22++σ82+σ92

Where, σ1, σ2, ...., σ8, σ9 are the standard deviation of each activity on the critical path   

Calculation:

Given:

σ1, σ2, ...., σ8, σ9 = 3

σcp = σ12+σ22++σ82+σ92

σcp32+32+32+32+32+32+32+32+32

σcp9×9 = 9

∴ the standard deviation of the critical path is 9.

Critical Path Question 5:

A PERT network has nine activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. 3
  2. 9
  3. 81
  4. 27

Answer (Detailed Solution Below)

Option 2 : 9

Critical Path Question 5 Detailed Solution

Concept:

In CPM:

The standard deviation of the critical path:

σcp Sumofvariancealongcriticalpath

σcp = σ12+σ22++σ82+σ92

Where, σ1, σ2, ...., σ8, σ9 are the standard deviation of each activity on the critical path   

Calculation:

Given:

σ1, σ2, ...., σ8, σ9 = 3

σcp = σ12+σ22++σ82+σ92

σcp = 32+32+32+32+32+32+32+32+32

σcp = 9×9 = 9

∴ the standard deviation of the critical path is 9.

Top Critical Path MCQ Objective Questions

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. 3
  2. 9
  3. 81
  4. 27

Answer (Detailed Solution Below)

Option 2 : 9

Critical Path Question 6 Detailed Solution

Download Solution PDF

Concept:

In CPM:

The standard deviation of critical path:

σcp Sumofvariancealongcriticalpath

σcpσ12+σ22++σ82+σ92

Where, σ1, σ2, ...., σ8, σ9 are the standard deviation of each activity on the critical path   

Calculation:

Given:

σ1, σ2, ...., σ8, σ9 = 3

σcp = σ12+σ22++σ82+σ92

σcp32+32+32+32+32+32+32+32+32

σcp9×9 = 9

∴ the standard deviation of the critical path is 9.

Critical path method is good for

  1. small project only
  2. large project only
  3. both small and large projects equally
  4. neither small nor large projects

Answer (Detailed Solution Below)

Option 2 : large project only

Critical Path Question 7 Detailed Solution

Download Solution PDF

Explanation:

Critical Path:

critical path is a sequence of interdependent activities or tasks that must be finished before the project can be finished. It is the longest path (i.e. path with the longest duration) from project start to finish.

Critical Path Method:

  • The critical path method (CPM) is a project modeling technique that’s used by project managers to find important deadlines and deliver a project on time.
  • In a project, the critical path is the longest distance between the start and the finish, including all the tasks and their duration.
  • Once a critical path is determined, you’ll have a clear picture of the project’s actual schedule.
  • To find this, project managers use the CPM algorithm to find the least amount of time necessary to complete each task with the least amount of slack.
  • For small projects, managers are often able to memorize and to coordinate all of the various tasks necessary for their completion.
  • For larger projects, however, with numerous activities occurring simultaneously, remembering and coordinating these activities can prove much more difficult. CPM and related tools allow managers to determine which particular tasks most affect the total time of the project and enable managers to better schedule each task so that deadlines are met at the least possible cost

The total float on the critical path in CPM is _________.

  1. negative
  2. positive fraction
  3. positive
  4. zero

Answer (Detailed Solution Below)

Option 4 : zero

Critical Path Question 8 Detailed Solution

Download Solution PDF

Explanation:

Critical Path:

  • The longest path in the network diagram is called the Critical Path.
  • The length of the Critical Path determines the minimum duration required for the completion of the project.

Critical activity:

  • Critical activities are those activities that lie on critical path.
  • The float of activities that lie on the critical path is zero.

Float:

  • Relax or delay provided to any activity is known as float.

Floats are of three types. They are as follows:

F1 Ashiq 21.9.20 Pallavi D18

Total Float (TF):

The maximum delay or relax provided to any activity without affecting the project duration.

TF = Lj – Ei – dij

Free Float (FF):

Relax or delay provided to any activity without affecting the Earliest Start Time (EST) of the successor activity.

FF = Ej – Ei – dij

Independent Float:

Relax or delay provided to any activity without affecting the Earliest Start Time (EST) of successor activity as well as Latest Finish Time (LFT) of the predecessor activity.

IF = Ej – Li - dij

Relation among float TF ≥ FF ≥ IF

On the Critical path, total, free, and independent float are all equal and zero.

Critical activities have

  1. maximum float
  2. minimum float
  3. zero float
  4. negative float

Answer (Detailed Solution Below)

Option 3 : zero float

Critical Path Question 9 Detailed Solution

Download Solution PDF

Explanation:

Critical activity:

Critical activities are those activities whose float is zero and they lie on the critical path.

Float:

Relax or delay provided to any activity is known as float.

Floats are of three types. They are as follows:

F1 Ashiq 21.9.20 Pallavi D18

Total Float (TF):

The maximum delay or relax provided to any activity without affecting the project duration.

TF = Lj – Ei – dij

Free Float (FF):

Relax or delay provided to any activity without affecting the Earliest Start Time (EST) of the successor activity.

FF = Ej – Ei – dij

Independent Float:

Relax or delay provided to any activity without affecting the Earliest Start Time (EST) of successor activity as well as Latest Finish Time (LFT) of the predecessor activity.

IF = Ej – Li - dij

Relation among float TF ≥ FF ≥ IF

26 June 1

Critical Path:

  • The longest path in the network diagram is called Critical Path.
  • The length of the Critical Path determines the minimum duration required for the completion of the project.

The given table lists the project's activities, precedence relationships and duration. Find the critical path of the project.

Activity Precedence Duration (in days)
P - 3
Q - 4
R P 5
S Q 5
T R, S 7
U R, S 5
V T 2
W U 10

  1. P-R-U-V
  2. P-R-T-U
  3. Q-S-T-U
  4. Q-S-U-W

Answer (Detailed Solution Below)

Option 4 : Q-S-U-W

Critical Path Question 10 Detailed Solution

Download Solution PDF

Explanation:

The project activities, precedence relationships are given below:
F1 Ateeb Madhuri 01.02.2022 D1

From the diagram we can conclude that the critical path is Q-S-U-W.

A PERT network has nine activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. 3
  2. 9
  3. 81
  4. 27

Answer (Detailed Solution Below)

Option 2 : 9

Critical Path Question 11 Detailed Solution

Download Solution PDF

Concept:

In CPM:

The standard deviation of the critical path:

σcp Sumofvariancealongcriticalpath

σcp = σ12+σ22++σ82+σ92

Where, σ1, σ2, ...., σ8, σ9 are the standard deviation of each activity on the critical path   

Calculation:

Given:

σ1, σ2, ...., σ8, σ9 = 3

σcp = σ12+σ22++σ82+σ92

σcp = 32+32+32+32+32+32+32+32+32

σcp = 9×9 = 9

∴ the standard deviation of the critical path is 9.

Which of the following statements is NOT true about critical path method (CPM)? 

  1. CPM is concerned with activities.
  2. CPM is suitable for non - repetitive projects.
  3. CPM cannot be analysed statistically.
  4. CPM establishes a relationship between time and cost.

Answer (Detailed Solution Below)

Option 2 : CPM is suitable for non - repetitive projects.

Critical Path Question 12 Detailed Solution

Download Solution PDF

Concept: 

Critical Path Method (CPM):

  • CPM is best suited for repetitive and predictable projects, like construction, maintenance, manufacturing, etc. It assumes known and fixed time estimates, which is not ideal for non-repetitive or highly uncertain projects.
  • CPM uses deterministic time estimates (i.e., fixed durations), so it doesn't involve statistical analysis like PERT (which uses probabilistic time estimates).
  • CPM helps in time-cost optimization, allowing for crashing of activities to reduce project duration at additional cost.

 

Program (Project) Evaluation and Review Technique (PERT):
  • Program Evaluation and Review Technique (PERT) is a method used to examine the tasks in a schedule and determine a Critical Path Method variation (CPM). It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project.
  • It estimates the shortest possible time each activity will take, the most likely length of time, and the longest time that might be taken if the activity takes longer than expected.  The US Navy developed the method in 1957 on the Polaris nuclear submarine project.

Additional Information

Difference between PERT and CPM

PERT

CPM

Project Evaluation and Review Technique

Critical Path Method

It is event-oriented.

It is activity-oriented.

It is associated with probabilistic activities.

It is associated with deterministic activities.

It is based upon a three-time estimate to complete an activity.

te=(to+4tm+tp6)

Where, te = expected time to complete an activity

to  = optimistic time, tm = mean time, t = pessimistic time

It is based upon a single time estimate to complete an activity.

It usually doesn’t consider cost analysis.

It gives importance to cost analysis & crashing is done to minimize the cost of the CPM project.

Applications: Mainly used for R & D project

Applications: Mainly used for Construction project

Activities falling on the critical path have

  1. zero slack
  2. maximum slack
  3. minimum slack
  4. negative slack

Answer (Detailed Solution Below)

Option 1 : zero slack

Critical Path Question 13 Detailed Solution

Download Solution PDF

Explanation:

Critical Path

  • Critical path activities are the project tasks that must start and finish on time according to schedule.
  • A delay in any critical path activity will delay the completion of the scheduled project.

Float or Slack in critical activity

  • Slack or float refers to the amount of time that various related tasks can be delayed without pushing the schedule.
  • Float is a measure of schedule flexibility.
  • The critical path, by definition, has no slack. But other tasks not on the critical path may have a built-in float.
  • If the Start date and Finish date for an activity are the same as the schedule, the activity is said to have zero floats.
  • Activities that have zero floats must start on time to prevent the schedule from slipping.
  • Critical activities can also have a negative float.
  • Negative float occurs when an activity finishes before the scheduled date.

Additional Information

Critical Path Method (CPM):

It is commonly used for those projects which are repetitive in nature and where one has prior experience of handling similar projects. Its is a deterministic model and places emphasis on time and cost for activities of a project.

  • A project can be defined as a set of large numbers of activities or jobs that are performed in a certain sequence determined.
  • A network is a graphical representation of a project, depicting the float as well as the sequence of well-defined activities and events.
  • An activity is any portion of a project which consumes time or resources and has a definable beginning and end.
  • Event is the beginning and ending point of activity or group of activities.

B-D-E-H is the critical path in the diagram below.

F1 Krupalu Madhu 28.10.20 D11

The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship “X < Y, Z” means that X is predecessor of activities Y and Z. The time to complete the activities along the critical path is ______ weeks.

Activity

Duration (weeks)

Precedence

Relationship

A

5

A < B, C, D

B

7

B < E, F, G

C

10

C < I

D

6

D < G

E

3

E < H

F

9

F < I

G

7

G < I

H

4

H < I

I

2

----

  1. 17
  2. 21
  3. 23
  4. 25

Answer (Detailed Solution Below)

Option 3 : 23

Critical Path Question 14 Detailed Solution

Download Solution PDF

We are asked to calculate the time along critical path. For complete analysis of critical path we need to do forward pass and backward pass computation. In this question only time is asked, and we know that the time along the critical path is maximum of all the paths in our network so we will directly evaluate the maximum time along any path and mark the answer to save time. Also forward and backward pass computation is necessary if we are asked to find critical path or float related parameters.

In this question “<” & “>” symbols are used to just describe the precedence relationship.

i.e. A < B means A occurs before B.

⇒ On constructing the network diagram with the given precedence relationship.

F3 S.S Madhu 28.11.19 D 9

  

A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:

Activity

Immediate predecessor

Duration (days)

A

-

4

B

A

3

C

A

7

D

B

14

E

C

4

F

D, E

9


The minimum project completion time (in days) is ________.

Answer (Detailed Solution Below) 30

Critical Path Question 15 Detailed Solution

Download Solution PDF

Capture 12345678910340

The minimum project completion time is 30 days.

Get Free Access Now
Hot Links: teen patti vungo teen patti master apk download teen patti master 2025 teen patti online