Critical Path MCQ Quiz in తెలుగు - Objective Question with Answer for Critical Path - ముఫ్త్ [PDF] డౌన్లోడ్ కరెన్
Last updated on Apr 8, 2025
Latest Critical Path MCQ Objective Questions
Top Critical Path MCQ Objective Questions
Critical Path Question 1:
In the Critical Path Method (CPM), what is the primary purpose of identifying the critical path?
Answer (Detailed Solution Below)
Critical Path Question 1 Detailed Solution
Critical Path Question 2:
A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is
Answer (Detailed Solution Below)
Critical Path Question 2 Detailed Solution
Concept:
In CPM:
The standard deviation of critical path:
σcp = \(\sqrt {Sum\;of\;variance\;along\;critical\;path} \)
σcp = \(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)
Where, σ1, σ2, ...., σ8, σ9 are the standard deviation of each activity on the critical path
Calculation:
Given:
σ1, σ2, ...., σ8, σ9 = 3
σcp = \(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)
σcp = \(\sqrt {3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2} \)
σcp = \(\sqrt {9 \times 9} \) = 9
∴ the standard deviation of the critical path is 9.
Critical Path Question 3:
A project consists of 7 activities with the following data.
Activity |
Predecessor |
Duration (days) |
A |
- |
4 |
B |
- |
3 |
C |
A |
3 |
D |
A |
5 |
E |
B, C |
5 |
F |
B, C |
6 |
G |
D, E |
8 |
What will be the minimum number of days to complete the project?
Answer (Detailed Solution Below) 20
Critical Path Question 3 Detailed Solution
Path |
Duration (days) |
A ─ D ─ G |
4 + 5 + 8 = 17 |
A ─ C ─ E ─ G |
4 + 3 + 5 + 8 = 20 (CP) |
B ─ E ─ G |
3 + 5 + 8 = 16 |
B ─ F |
3 + 6 = 9 |
A ─ C ─ F |
4 + 3 + 6 = 13 |
∴ Minimum time required to complete project = 20 days
Critical Path Question 4:
A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is _______
Answer (Detailed Solution Below) 14
Critical Path Question 4 Detailed Solution
Concept:
The critical path is the maximum duration of the project if all the activities are completed within the time. Hence first we will find the critical path. Then we will see that how many days are still left before node 10 contributes to the path of the critical path. And the number of days by which we can delay that activity without affecting the overall duration of the project will be our answer
Critical path = 1 – 2 – 4 – 7 – 9 – 11 – 12, Total time = 19 days
Earliest finish time for node 10 = 9 days
After that, we still need 3 days to complete that activity and then that path too will be joined to the critical path at node 11. Hence the maximum time we have to complete the activity after node 10 will be 17 days and we need 3 days to complete the activity hence we can delay the activity before node 10 upto (17 – 3)days i.e. 14 days
∴ Latest finish time for node 10 = 14 days
Additional Information The latest finish time:
- The latest finish time is the latest possible date and time by which a project segment can be completed without negatively impacting the completion date for an entire project.
- If the latest finish time is exceeded, it delays the start time of the next project segment, and therefore the completion of the project as a whole. The concept is used in the planning of projects using the program evaluation and review technique (PERT).
Critical Path Question 5:
Task |
Precedence |
Normal duration (weeks) |
A |
- |
16 |
B |
- |
20 |
C |
A |
8 |
D |
A |
10 |
E |
B, C |
6 |
F |
D, E |
12 |
From the given table of a project the critical path, the project duration and the free float for activity A are respectively
Answer (Detailed Solution Below)
Critical Path Question 5 Detailed Solution
Draw network diagram
From the network diagram we get critical path as A – C – E – F
Project duration = 16 + 8 + 6 + 12 = 42 weeks
Free float of activity A
Free float, FF = Ej – (Ei + tij)
FF = 16 – (0 + 16) = 0
Points to remember:
i) Free float FF = Ej – (Ei + tij)
ii) Project duration is total time on critical pathCritical Path Question 6:
The arc lengths of a directed graph of a project are as shown in the figure. The shortest path length from node 1 to node 6 is _______.
Answer (Detailed Solution Below) 7
Critical Path Question 6 Detailed Solution
Explanation:
Here the shortest path length from node 1 to node 6 is asked.
So, the resultant is
\(\left( 1 \right)\mathop \to \limits^2 \left( 2 \right)\mathop \to \limits^2 \left( 5 \right)\mathop \to \limits^1 \left( 4 \right)\mathop \to \limits^2 \left( 6 \right)\)
Length = 2 + 2 + 1 + 2 = 7
Mistake Point: Here don’t confuse with the critical path
\(\left( 1 \right)\mathop \to \limits^4 \left( 3 \right)\mathop \to \limits^3 \left( 5 \right)\mathop \to \limits^2 \left( 6 \right)\)
4 + 3 + 4 = 11Critical Path Question 7:
Given network represents a project:
Three time involved are written on arrows. Calculate the critical path for the network.
Answer (Detailed Solution Below)
Critical Path Question 7 Detailed Solution
First calculate expected time (tE) for each path \(= \frac{{{t_o} + 4{t_m} + {t_p}}}{6}\)
Where, to = Optimistic time
tp = Pessimistic time
tm = Most likely time
Activity |
Times |
Expected time (te) \({t_e} = \frac{{{t_o} + 4{t_m} + {t_p}}}{6}\) |
||
|
to |
tm |
tp |
|
A |
5 |
7 |
9 |
7 |
B |
6 |
7 |
8 |
7 |
C |
1 |
2 |
3 |
2 |
D |
3 |
6 |
9 |
6 |
E |
4 |
8 |
12 |
8 |
F |
4 |
5 |
6 |
5 |
G |
5 |
7 |
9 |
7 |
H |
6 |
8 |
10 |
8 |
I |
2 |
4 |
6 |
4 |
Critical Path Question 8:
. A project consists of following activities:
Activity |
Predecessor |
Estimated duration (in days) |
||
Optimistic |
Most-likely |
Pessimistic |
||
A |
- |
1 |
1 |
7 |
B |
- |
1 |
4 |
7 |
C |
- |
2 |
2 |
8 |
D |
A |
1 |
1 |
1 |
E |
B |
2 |
5 |
14 |
F |
C |
2 |
5 |
8 |
G |
D, E |
3 |
6 |
15 |
H |
F, G |
1 |
2 |
3 |
The expected project completion time is
Answer (Detailed Solution Below)
Critical Path Question 8 Detailed Solution
Explanation:
The expected time for each activity,
\({t_e} = \frac{{{t_0}\; + \;4{t_m}\; + \;{t_p}}}{6}\)
Where,
t0 → optimistic time
tm → most-likely time
tp → pessimistic time
Activity |
t0 |
tm |
tp |
\({t_e} = \frac{{{t_0}\; + \;4{t_m}\; + \;{t_p}}}{6}\) |
A |
1 |
1 |
7 |
2 |
B |
1 |
4 |
7 |
4 |
C |
2 |
2 |
8 |
3 |
D |
1 |
1 |
1 |
1 |
E |
2 |
5 |
14 |
6 |
F |
2 |
5 |
8 |
5 |
G |
3 |
6 |
15 |
7 |
H |
1 |
2 |
3 |
2 |
Now, plotting the network diagram and showing the activity duration using ‘te’
From the above, network diagram, it is clear that 1 – 3 – 5 – 6 – 7 is critical path.
∴ Expected project duration = 19 days
Critical Path Question 9:
Statement I): The change in the critical path requires rescheduling in a PERT network.
Statement II): Some of the activities cannot be completed in time due to an unexpected breakdown of equipment or non-availability of raw materialsAnswer (Detailed Solution Below)
Critical Path Question 9 Detailed Solution
Explanation:
- A project may be defined as a combination of interrelated activities which must be executed in a certain order before the entire task can be completed.
- The aim of planning is to develop a sequence of activities of the project so that the project completion time and cost are properly balanced.
- To meet the objective of systematic planning, the management has evolved several techniques applying network strategy.
- PERT (Programme Evaluation and Review Technique) and CPM (Critical Path Method) are network techniques which have been widely used for planning, scheduling and controlling the large and complex projects.
Difference between PERT and CPM (Critical Path Method)
PERT |
CPM |
1. Probabilistic approach |
1. Deterministic approach |
2. Three-time estimate |
2. One - time estimate |
3. Event oriented network model |
3. Activity-oriented network model |
4. The slack concept is used |
4. Float concept is used |
5. Project crashing is not possible |
5. Project crashing is possible |
6. Deals with probabilistic time estimates |
6. Deals with deterministic time estimates |
- Any change in the critical path will determine the change in the project duration So, a change in the critical path requires the rescheduling of the PERT network.
- These changes may happen due to an unexpected breakdown of equipment or the non-availability of raw materials.
So, both statements are individually correct.
Critical Path Question 10:
The critical path in PERT/CPM is
Answer (Detailed Solution Below)
Critical Path Question 10 Detailed Solution
Explanation:
Critical Path Method (CPM):
- The sequence of critical activities in a network is called the critical path. The critical path is denoted by double lines. It is the longest path in the network from the starting to the ending event and defines the minimum time required to complete the project.
- CPM revolves around discovering the most important tasks in the project timeline, identifying task dependencies, and calculating task durations.
- CPM was developed in the late 1950s as a method to resolve the issue of increased costs due to inefficient scheduling. Since then, CPM has become popular for planning projects and prioritizing tasks.
Program Evolution and Review Technique (PERT):
- Program Evaluation and Review Technique (PERT) is a method used to examine the tasks in a schedule and determine a Critical Path Method variation (CPM). It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project.
- It estimates the shortest possible time each activity will take, the most likely length of time, and the longest time that might be taken if the activity takes longer than expected. The US Navy developed the method in 1957 on the Polaris nuclear submarine project.
Additional Information
Difference between PERT and CPM
PERT |
CPM |
Project Evaluation and Review Technique |
Critical Path Method |
It is event-oriented. |
It is activity-oriented. |
It is associated with probabilistic activities. |
It is associated with deterministic activities. |
It is based upon a three-time estimate to complete an activity. \({t_e} = \left( {\frac{{{t_o} + 4{t_m} + {t_p}}}{6}} \right)\) Where, te = expected time to complete an activity to = optimistic time, tm = mean time, tp = pessimistic time |
It is based upon a single time estimate to complete an activity. |
It usually doesn’t consider cost analysis. |
It gives importance to cost analysis & crashing is done to minimize the cost of the CPM project. |
Applications: Mainly used for R & D project |
Applications: Mainly used for Construction project |