Critical Path MCQ Quiz in বাংলা - Objective Question with Answer for Critical Path - বিনামূল্যে ডাউনলোড করুন [PDF]

Last updated on Apr 10, 2025

পাওয়া Critical Path उत्तरे आणि तपशीलवार उपायांसह एकाधिक निवड प्रश्न (MCQ क्विझ). এই বিনামূল্যে ডাউনলোড করুন Critical Path MCQ কুইজ পিডিএফ এবং আপনার আসন্ন পরীক্ষার জন্য প্রস্তুত করুন যেমন ব্যাঙ্কিং, এসএসসি, রেলওয়ে, ইউপিএসসি, রাজ্য পিএসসি।

Latest Critical Path MCQ Objective Questions

Top Critical Path MCQ Objective Questions

Critical Path Question 1:

Some activities of a project are given in a table with immediate predecessor & duration

Activity

Immediate predecessor

Duration of activity (days)

A

-

12 days

B

A

8

C

A

4

D

A

3

E

B

12

F

C

18

G

C

5

H

E, F

4

I

D, G

9

J

H, I

6

 

Calculate the shortest project duration time? 

Answer (Detailed Solution Below) 44

Critical Path Question 1 Detailed Solution

GATE ME Industrial Engineering part-3 +4 images Q10

Critical path is A – C – F – H – J

Thus, project duration time = 12 + 4 + 18 + 4 + 6 = 44 days

Critical Path Question 2:

In the Critical Path Method (CPM), what is the primary purpose of identifying the critical path?

  1. To calculate the average time required for project completion
  2. To determine the least expensive way to complete the project
  3. To identify the longest sequence of dependent tasks that dictates the project's completion time
  4. To find the most efficient allocation of resources across tasks

Answer (Detailed Solution Below)

Option 3 : To identify the longest sequence of dependent tasks that dictates the project's completion time

Critical Path Question 2 Detailed Solution

In the Critical Path Method (CPM), the primary purpose of identifying the critical path is to determine the longest sequence of dependent tasks that dictates the project's completion time. The critical path represents the chain of tasks that directly affect the project's finish date. Any delay in these tasks will result in a delay in the overall project. Understanding the critical path is essential for effective project scheduling and management, ensuring that critical tasks are prioritized to meet project deadlines.

Critical Path Question 3:

A project consists of 7 activities with the following data.

Activity

Predecessor

Duration (days)

A

-

4

B

-

3

C

A

3

D

A

5

E

B, C

5

F

B, C

6

G

D, E

8

 

What will be the minimum number of days to complete the project?

Answer (Detailed Solution Below) 20

Critical Path Question 3 Detailed Solution

F1 S.C Madhu 11.06.20 D 1

Path

Duration (days)

A ─ D ─ G

4 + 5 + 8 = 17

A ─ C ─ E ─ G

4 + 3 + 5 + 8 = 20 (CP)

B ─ E ─ G

3 + 5 + 8 = 16

B ─ F

3 + 6 = 9

A ─ C ─ F

4 + 3 + 6 = 13

 

∴ Minimum time required to complete project = 20 days

Critical Path Question 4:

A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is _______

F1 S.S Madhu 19.11.19 D 5

Answer (Detailed Solution Below) 14

Critical Path Question 4 Detailed Solution

F1 S.S Madhu 19.11.19 D 6

Concept:

The critical path is the maximum duration of the project if all the activities are completed within the time. Hence first we will find the critical path. Then we will see that how many days are still left before node 10 contributes to the path of the critical path. And the number of days by which we can delay that activity without affecting the overall duration of the project will be our answer

Critical path = 1 – 2 – 4 – 7 – 9 – 11 – 12, Total time = 19 days

Earliest finish time for node 10 = 9 days

After that, we still need 3 days to complete that activity and then that path too will be joined to the critical path at node 11. Hence the maximum time we have to complete the activity after node 10 will be 17 days and we need 3 days to complete the activity hence we can delay the activity before node 10 upto (17 – 3)days i.e. 14 days

∴ Latest finish time for node 10 = 14 days

Additional Information The latest finish time:

  • The latest finish time is the latest possible date and time by which a project segment can be completed without negatively impacting the completion date for an entire project.
  • If the latest finish time is exceeded, it delays the start time of the next project segment, and therefore the completion of the project as a whole. The concept is used in the planning of projects using the program evaluation and review technique (PERT).

Critical Path Question 5:

Task

Precedence

Normal duration (weeks)

A

-

16

B

-

20

C

A

8

D

A

10

E

B, C

6

F

D, E

12

 

From the given table of a project the critical path, the project duration and the free float for activity A are respectively

  1. A – C – E – F, 50 weeks & 0 week
  2. A – C – E – F, 42 weeks & 0 week
  3. A – D – F, 38 weeks & 2 weeks
  4. B – E – F, 38 weeks & 0 week

Answer (Detailed Solution Below)

Option 2 : A – C – E – F, 42 weeks & 0 week

Critical Path Question 5 Detailed Solution

Draw network diagram

F1 S.S Pallavi 10.12.19 D5

From the network diagram we get critical path as A – C – E – F

Project duration = 16 + 8 + 6 + 12 = 42 weeks

Free float of activity A

F1 S.S Pallavi 10.12.19 D9

Free float, FF = Ej – (Ei + tij)

FF = 16 – (0 + 16) = 0

Points to remember:

i) Free float FF = Ej – (Ei + tij)

ii) Project duration is total time on critical path

Critical Path Question 6:

The arc lengths of a directed graph of a project are as shown in the figure. The shortest path length from node 1 to node 6 is _______.

F2 S.S D.K 04.09.2019 D20

Answer (Detailed Solution Below) 7

Critical Path Question 6 Detailed Solution

Explanation:

Here the shortest path length from node 1 to node 6 is asked.

So, the resultant is

\(\left( 1 \right)\mathop \to \limits^2 \left( 2 \right)\mathop \to \limits^2 \left( 5 \right)\mathop \to \limits^1 \left( 4 \right)\mathop \to \limits^2 \left( 6 \right)\)

Length = 2 + 2 + 1 + 2 = 7

Mistake Point: Here don’t confuse with the critical path

\(\left( 1 \right)\mathop \to \limits^4 \left( 3 \right)\mathop \to \limits^3 \left( 5 \right)\mathop \to \limits^2 \left( 6 \right)\)

4 + 3 + 4 = 11

Critical Path Question 7:

Given network represents a project:

23

Three time involved are written on arrows. Calculate the critical path for the network.

  1. 1 – 2 – 3 – 5 – 7 – 8
  2. 1 – 2 – 3 – 4 – 6 – 7 – 8
  3. Both 1 – 2 – 3 – 5 – 7 – 8 & 1 – 2 – 3 – 4 – 6 – 7 – 8
  4. 1 – 2 – 3 – 7 – 8

Answer (Detailed Solution Below)

Option 2 : 1 – 2 – 3 – 4 – 6 – 7 – 8

Critical Path Question 7 Detailed Solution

First calculate expected time (tE) for each path \(= \frac{{{t_o} + 4{t_m} + {t_p}}}{6}\)

Where, to = Optimistic time

tp = Pessimistic time

tm = Most likely time

Activity

Times

Expected time (te)

\({t_e} = \frac{{{t_o} + 4{t_m} + {t_p}}}{6}\)

 

to

tm

tp

A

5

7

9

7

B

6

7

8

7

C

1

2

3

2

D

3

6

9

6

E

4

8

12

8

F

4

5

6

5

G

5

7

9

7

H

6

8

10

8

I

2

4

6

4

 

cp235676

Critical path ⇒ 1 – 2 – 3 – 4 – 6 – 7 – 8

Critical Path Question 8:

. A project consists of following activities:

Activity

Predecessor

Estimated duration (in days)

Optimistic

Most-likely

Pessimistic

A

-

1

1

7

B

-

1

4

7

C

-

2

2

8

D

A

1

1

1

E

B

2

5

14

F

C

2

5

8

G

D, E

3

6

15

H

F, G

1

2

3

 

The expected project completion time is

  1. 16 days
  2. 18 days
  3. 19 days
  4. 20 days

Answer (Detailed Solution Below)

Option 3 : 19 days

Critical Path Question 8 Detailed Solution

Explanation:

The expected time for each activity,

\({t_e} = \frac{{{t_0}\; + \;4{t_m}\; + \;{t_p}}}{6}\)

Where,

t0 → optimistic time

tm → most-likely time

tp → pessimistic time

Activity

t­0

tm

tp

\({t_e} = \frac{{{t_0}\; + \;4{t_m}\; + \;{t_p}}}{6}\)

A

1

1

7

2

B

1

4

7

4

C

2

2

8

3

D

1

1

1

1

E

2

5

14

6

F

2

5

8

5

G

3

6

15

7

H

1

2

3

2

 

Now, plotting the network diagram and showing the activity duration using ‘te

F1 S.C 21.7.20 Pallavi D3

From the above, network diagram, it is clear that 1 – 3 – 5 – 6 – 7 is critical path.

∴ Expected project duration = 19 days

Critical Path Question 9:

Statement I): The change in the critical path requires rescheduling in a PERT network.

Statement II): Some of the activities cannot be completed in time due to an unexpected breakdown of equipment or non-availability of raw materials

  1. Both Statements I) and Statement II) are individually true and Statement II) is the correct explanation of Statement I)
  2. Both Statements I) and Statement II) are individually true but Statement II) is not the correct explanation of Statement I)
  3. Statement I) is true but Statement II) is false
  4. Statement I) is false but Statement II) is true

Answer (Detailed Solution Below)

Option 2 : Both Statements I) and Statement II) are individually true but Statement II) is not the correct explanation of Statement I)

Critical Path Question 9 Detailed Solution

Explanation:

  • A project may be defined as a combination of interrelated activities which must be executed in a certain order before the entire task can be completed.
  • The aim of planning is to develop a sequence of activities of the project so that the project completion time and cost are properly balanced.
  • To meet the objective of systematic planning, the management has evolved several techniques applying network strategy.
  • PERT (Programme Evaluation and Review Technique) and CPM (Critical Path Method) are network techniques which have been widely used for planning, scheduling and controlling the large and complex projects.

Difference between PERT and CPM (Critical Path Method)

PERT

CPM

1. Probabilistic approach

1. Deterministic approach

2. Three-time estimate

2. One - time estimate

3. Event oriented network model

3. Activity-oriented network model

4. The slack concept is used

4. Float concept is used

5. Project crashing is not possible

5. Project crashing is possible

6. Deals with probabilistic time estimates

6. Deals with deterministic time estimates

  • Any change in the critical path will determine the change in the project duration So, a change in the critical path requires the rescheduling of the PERT network.
  • These changes may happen due to an unexpected breakdown of equipment or the non-availability of raw materials.

So, both statements are individually correct.

Critical Path Question 10:

The critical path in PERT/CPM is

  1. The shortest path in the network from the start to the end and defines the minimum time to complete the project.
  2. The longest path in the network from the start to end and defines the maximum time to complete the project.
  3. The shortest path in the network from the start to the end and defines the maximum time to complete the project.
  4. The longest path in the network from the start to the end and defines the minimum time to complete the project.

Answer (Detailed Solution Below)

Option 4 : The longest path in the network from the start to the end and defines the minimum time to complete the project.

Critical Path Question 10 Detailed Solution

Explanation:

Critical Path Method (CPM):

  • The sequence of critical activities in a network is called the critical path. The critical path is denoted by double lines. It is the longest path in the network from the starting to the ending event and defines the minimum time required to complete the project.
  • CPM revolves around discovering the most important tasks in the project timeline, identifying task dependencies, and calculating task durations.
  • CPM was developed in the late 1950s as a method to resolve the issue of increased costs due to inefficient scheduling. Since then, CPM has become popular for planning projects and prioritizing tasks.

Program Evolution and Review Technique (PERT):

  • Program Evaluation and Review Technique (PERT) is a method used to examine the tasks in a schedule and determine a Critical Path Method variation (CPM). It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project.
  • It estimates the shortest possible time each activity will take, the most likely length of time, and the longest time that might be taken if the activity takes longer than expected.  The US Navy developed the method in 1957 on the Polaris nuclear submarine project.

Additional Information

Difference between PERT and CPM

PERT

CPM

Project Evaluation and Review Technique

Critical Path Method

It is event-oriented.

It is activity-oriented.

It is associated with probabilistic activities.

It is associated with deterministic activities.

It is based upon a three-time estimate to complete an activity.

\({t_e} = \left( {\frac{{{t_o} + 4{t_m} + {t_p}}}{6}} \right)\)

Where, te = expected time to complete an activity

to  = optimistic time, tm = mean time, t = pessimistic time

It is based upon a single time estimate to complete an activity.

It usually doesn’t consider cost analysis.

It gives importance to cost analysis & crashing is done to minimize the cost of the CPM project.

Applications: Mainly used for R & D project

Applications: Mainly used for Construction project

Get Free Access Now
Hot Links: teen patti go teen patti joy 51 bonus teen patti master app teen patti teen patti game paisa wala