Question
Download Solution PDFWhich type of formwork requires a maximum stripping time of 14 days?
This question was previously asked in
DDA JE Civil 29 Mar 2023 Shift 2 Official Paper
Answer (Detailed Solution Below)
Option 2 : Props to slabs spanning over 4.5 m
Free Tests
View all Free tests >
DDA JE Civil Full Mock Test
7.1 K Users
120 Questions
120 Marks
120 Mins
Detailed Solution
Download Solution PDFExplanation:
Type of formwork | Minimum period before sticking formwork |
Vertical formwork to columns, beams, and walls | 16 - 24 hour |
Soffit formwork to slabs (props to be refixed immediately after removal of formwork) | 3 days |
Soffit formwork to beams (props to be refixed immediately after removal of formwork) | 7 days |
Props to slab | |
|
7 days |
|
14 days |
Props to beams | |
|
14 days |
|
21 days |
Last updated on May 28, 2025
-> The DDA JE Recruitment 2025 Notification will be released soon.
-> A total of 1383 vacancies are expected to be announced through DDA recruitment.
-> Candidates who want a final selection should refer to the DDA JE Previous Year Papers to analyze the pattern of the exam and improve their preparation.
-> The candidates must take the DDA JE Electrical/Mechanical mock tests or DDA JE Civil Mock tests as per their subject.