In progress of a project, the percentage of error will be less in

This question was previously asked in
UPSC ESE 2019 Paper 1
View all UPSC IES Papers >
  1. Definitive cost estimate
  2. Detailed estimate
  3. Preliminary estimate
  4. Study estimate

Answer (Detailed Solution Below)

Option 1 : Definitive cost estimate
Free
ST 1: UPSC ESE (IES) Civil - Building Materials
6.5 K Users
20 Questions 40 Marks 24 Mins

Detailed Solution

Download Solution PDF

Explanation:

Definitive cost estimate provides an accurate estimate of project costs. It is used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs. The accuracy of this type of estimate is normally -5 percent to +10 percent.

 

 

Life Cycle State

Type of Cost Estimate

1.

Initial (concept) stage

Rough order magnitude or Indicative cost estimate

2.

Planning and Design

Preliminary cost estimate

3.

Implementation or trending stage

Detailed cost estimate

4.

Closure stage

Definite cost estimate

 

As the project progress the error in cost estimation of the project decreases sharply from the rough order of magnitude estimates to definitive cost estimate.

Latest UPSC IES Updates

Last updated on Jul 2, 2025

-> ESE Mains 2025 exam date has been released. As per the schedule, UPSC IES Mains exam 2025 will be conducted on August 10. 

-> UPSC ESE result 2025 has been released. Candidates can download the ESE prelims result PDF from here.

->  UPSC ESE admit card 2025 for the prelims exam has been released. 

-> The UPSC IES Prelims 2025 will be held on 8th June 2025.

-> The selection process includes a Prelims and a Mains Examination, followed by a Personality Test/Interview.

-> Candidates should attempt the UPSC IES mock tests to increase their efficiency. The UPSC IES previous year papers can be downloaded here.

More Project Management Questions

Get Free Access Now
Hot Links: teen patti live teen patti rummy teen patti master game teen patti wala game teen patti master gold download