Gantt chart provides information about

This question was previously asked in
ISRO LPSC Technical Assistant Mechanical 4 March 2018 Official Paper
View all ISRO Technical Assistant Papers >
  1. Breakeven point analysis
  2. Material handling layout
  3. Production schedule
  4. Determining selling price

Answer (Detailed Solution Below)

Option 3 : Production schedule
Free
ISRO Technical Assistant Mechanical Full Mock Test
2.6 K Users
80 Questions 80 Marks 90 Mins

Detailed Solution

Download Solution PDF

Explanation:

Gantt Chart

  • These are mainly used to allocate resources to activities.
  • The resources allocated to activities include staff, hardware, and software.
  • These are useful for resource planning.
  • It is a special type of bar chart where each bar represents an activity.
  • The bars are drawn along a timeline.
  • The length of each bar is proportional to the duration of time planned for the corresponding activity, so it represents the production schedule.

1236986

Latest ISRO Technical Assistant Updates

Last updated on May 30, 2025

-> The ISRO Technical Assistant recruitment 2025 notification has been released at the official website. 

-> Candidates can apply for ISRO recruitment 2025 for Technical Assistant from June 4 to 18.

-> A total of 83 vacancies have been announced for the post of Technical Assistant.

-> The Selection process consists of a written test and a Skill test.

-> Candidates can also practice through ISRO Technical Assistant Electrical Test Series, ISRO Technical Assistant Electronics Test Series, and ISRO Technical Assistant Mechanical Test Series to improve their preparation and increase the chance of selection. 

Get Free Access Now
Hot Links: teen patti master 2025 teen patti circle teen patti joy official teen patti master purana