Question
Download Solution PDFA three phase transmission line delivers a load of 5 MW at 0.8 power factor lagging. Resistance of each conductor is 0.5 ohm / km. Receiving end voltage is 33 kV. If the line loss is not to exceed 10%, determine the length of the line.
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFExplanation:
Three-Phase Transmission Line Problem
Given Data:
- Load Power (Pload) = 5 MW = 5000 kW
- Power Factor (PF) = 0.8 (lagging)
- Resistance of each conductor (R) = 0.5 Ω/km
- Receiving end voltage (VR) = 33 kV = 33,000 V
- Maximum allowable line loss = 10%
To determine: The maximum length of the transmission line (L) such that the line loss does not exceed 10%.
Solution:
The transmission line loss is caused by the resistance of the conductors. To compute the maximum length of the line, we follow these steps:
The total power delivered to the load (Pload) is 5000 kW. The maximum allowable line loss is 10% of the load power:
Ploss = 10% × Pload = 0.1 × 5000 = 500 kW
The line current (I) can be calculated using the formula:
I = Pload / (√3 × VR × PF)
Substitute the given values:
I = 5000 × 103 / (√3 × 33,000 × 0.8)
I ≈ 109.07 A
The power loss in the transmission line is given by:
Ploss = 3 × I² × Rtotal
Here, Rtotal is the total resistance of the line, which depends on the length of the line (L):
Rtotal = 2 × R × L (since current flows through the forward and return paths of the line)
Substitute Rtotal into the formula for Ploss:
Ploss = 3 × I² × (2 × R × L)
Ploss = 6 × I² × R × L
Rearrange the formula to solve for L:
L = Ploss / (6 × I² × R)
Substitute the known values:
L = (500 × 10³) / (6 × (109.07)² × 0.5)
L ≈ 7 km
- Calculate the total line loss:
- Calculate the line current:
- Relate the line loss to resistance and current:
- Solve for the length of the line (L):
Final Answer: The maximum length of the transmission line is 7 km.
Additional Information
To further understand the analysis, let’s evaluate the other options:
Option 2: 27.9 km
If the length of the line were 27.9 km, the power loss would exceed the allowable 10% limit. This is because the resistance of the line would increase significantly, resulting in a higher power dissipation (Ploss = 6 × I² × R × L). Thus, this option is incorrect.
Option 3: 56.8 km
A line length of 56.8 km is much longer than the maximum permissible length (7 km). At this length, the power loss would be excessively high, far exceeding the 10% limit. Hence, this option is also incorrect.
Option 4: 13.9 km
While 13.9 km is closer to 7 km than the other options, it still exceeds the maximum permissible length. At this length, the power loss would be greater than the 10% limit, making this option incorrect as well.
Conclusion:
From the calculations and analysis, the correct option is Option 1: 7 km. This is the maximum length of the transmission line for which the line losses do not exceed 10% of the total load power.
Last updated on Jul 1, 2025
-> JKSSB Junior Engineer recruitment exam date 2025 for Civil and Electrical Engineering has been rescheduled on its official website.
-> JKSSB JE exam will be conducted on 31st August (Civil), and on 24th August 2025 (Electrical).
-> JKSSB JE application form correction facility has been started. Candidates can make corrections in the JKSSB recruitment 2025 form from June 23 to 27.
-> JKSSB JE recruitment 2025 notification has been released for Civil Engineering.
-> A total of 508 vacancies has been announced for JKSSB JE Civil Engineering recruitment 2025.
-> JKSSB JE Online Application form will be activated from 18th May 2025 to 16th June 2025
-> Candidates who are preparing for the exam can access the JKSSB JE syllabus PDF from official website of JKSSB.
-> The candidates can check the JKSSB JE Previous Year Papers to understand the difficulty level of the exam.
-> Candidates also attempt the JKSSB JE Mock Test which gives you an experience of the actual exam.