Question
Download Solution PDFA construction schedule is prepared after collecting:
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFExplanation:
Scheduling:
- Scheduling is deciding the phasing rate of activities with the starting and completion dates and the sequential relationship among the various activities in a project such that work can be carried out in an orderly and effective manner.
- It defines the roles of every member associated with the project and all the different types of resources required.
- A construction schedule is prepared after collecting the number of operations, output of labour and machinery, quantity of various items required, and many other things.
- In simple words we can say that scheduling is decide the order of all the activities and allocation of resources (like time, space, equipment/machinery, material, and manpower/labour) to the activities.
Last updated on Mar 4, 2025
-> OSSC Combined Technical Services Exam Mains (2023) Exam Date is out! The OSSC CTSRE Mains will be conducted on 15th March, 2025.
-> The OSSC CTSRE Prelims Answer Key for the 2023 cycle has been released for the Junior Engineer posts. The exam will be held on 9th June 2024. Candidates could raise objections online till 14th June 2024.
-> OSSC CTSRE 2024 Notification has been released.
-> A total of 381 vacancies have been announced under various Departments for the post of Junior Engineers & Junior Motor Vehicle Inspector.
-> Candidates can apply for the posts from 2nd April 2024 to 1st May 2024.
-> The examination will comprise 3 stages- Prelims, Mains, and Certificate Verification.
-> Prepare for the exam OSSC CTSRE Previous Year Papers.