What is the meaning of the term 'load factor'?

This question was previously asked in
SSC JE Electrical 07 Jun 2024 Shift 3 Official Paper - 1
View all SSC JE EE Papers >
  1. The ratio of total energy consumption to total energy production
  2. The ratio of peak load to average load over a year
  3. The ratio of average load to peak load over a year
  4. The ratio of total energy production to total energy consumption

Answer (Detailed Solution Below)

Option 3 : The ratio of average load to peak load over a year
Free
Electrical Machine for All AE/JE EE Exams Mock Test
7.7 K Users
20 Questions 20 Marks 20 Mins

Detailed Solution

Download Solution PDF

Load factor

Load factor is a measure of the efficiency with which electrical energy is used.

It is defined as the ratio of the average load over a given period to the maximum load during that same period.

\(Load \space factor={Average \space load\over Maximum\space load}\)

Significance:

  • A higher load factor indicates a more consistent and efficient use of electrical energy, which can lead to reduced operational costs.
  • A lower load factor suggests that there is a significant difference between the average load and the peak load, meaning energy usage is inconsistent, which can lead to inefficiencies and higher costs.

Additional Information Demand factor: It is defined as the ratio of maximum demand on the power station to its connected load.

\(Demand \space factor={Maximum \space demand\over Connected \space load}\)
 Utilization factor: It is the ratio of maximum demand on the power station to the rated capacity of the power station.

\(Utilisation \space factor={Maximum \space demand\over Rated \space capacity}\)

Diversity factor: The sum of individual maximum demands to the maximum demand on the power station is known as a diversity factor.

\(Diversity \space factor={Sum\space of \space individual\space maximum\space demands\over Maximum\space demand\space on \space power \space station}\)

Plant capacity factor: It is the ratio of actual energy produced to the maximum possible energy that could have been made during a given period.

\(Plant \space capacity \space factor={Average \space demand\over Plant\space capacity}\)

Latest SSC JE EE Updates

Last updated on Jul 1, 2025

-> SSC JE Electrical 2025 Notification is released on June 30 for the post of Junior Engineer Electrical, Civil & Mechanical.

-> There are a total 1340 No of vacancies have been announced. Categtory wise vacancy distribution will be announced later.

-> Applicants can fill out the SSC JE application form 2025 for Electrical Engineering from June 30 to July 21.

-> SSC JE EE 2025 paper 1 exam will be conducted from October 27 to 31. 

-> Candidates with a degree/diploma in engineering are eligible for this post.

-> The selection process includes Paper I and Paper II online exams, followed by document verification.

-> Prepare for the exam using SSC JE EE Previous Year Papers.

Get Free Access Now
Hot Links: teen patti master 2025 teen patti real teen patti download teen patti casino download