Comprehension

Consider the following PERT network: The optimistic time, most likely time and pessimistic time of all the activities are given in the table below:

Activity

 

Optimistic

time (days)

Most likely

time (days)

Pessimistic

time (days)

1 – 2

1

2

3

1 – 3

5

6

7

1 – 4

3

5

7

2 – 5

5

7

9

3 – 5

2

4

6

5 – 6

4

5

6

4 – 7

4

6

8

6 – 7

2

3

4

The critical path duration of the network (in days) is

This question was previously asked in
GATE ME 2009 Official Paper
View all GATE ME Papers >
  1. 11
  2. 14
  3. 17
  4. 18

Answer (Detailed Solution Below)

Option 4 : 18
Free
GATE ME 2023: Full Mock Test
65 Qs. 100 Marks 180 Mins

Detailed Solution

Download Solution PDF

Activity

Optimistic time (T0)

Most likely Time(Tm)

Ppessimistic

Time (TP)

expected

completion

 time (Te)

Variance

1 – 2

1

2

3

1 – 3

5

6

7

1 – 4

3

5

7

2 – 5

5

7

9

3 – 5

2

4

6

5 – 6

4

5

6

4 – 7

4

6

8

6 – 7

2

3

4

hence path 1 – 3 – 5 – 6 – 7  is the critical path, which has 18 days of expected completion time

Latest GATE ME Updates

Last updated on Feb 19, 2024

-> GATE ME Answer Key has been released. The exam was held on 3rd, 4th, 10th, and 11th February 2024.

-> The Graduate Aptitude Test in Engineering, also known as GATE, conducts an Entrance exam that serves as a gateway for all Engineering aspirants.

->  Candidates who want a successful selection can refer to the GATE ME Preparation Tips to boost their exam preparation and increase their chances of selection.

->  Candidates must attempt the GATE ME Mock tests

More Operations Research Questions

Hot Links: teen patti joy apk teen patti master online teen patti tiger yono teen patti teen patti master apk