Question
Download Solution PDFThe technique which is activity oriented is :
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFConcept:
PERT stands for "Project Evaluation and Review Technique"
CPM stand for "Critical Path Method"
Difference between PERT and CPM:
PERT |
CPM |
1. Probabilistic approach |
1. Deterministic approach |
2. Three-time estimate |
2. One-time estimate |
3. Event-oriented network model |
3. Activity-oriented network |
4. The slack concept is used |
4. Float concept is used |
5. Project crashing is not possible |
5. Project crashing is possible |
6. Deals with probabilistic time estimates |
6. Deals with deterministic time estimates |
Last updated on Mar 26, 2025
-> UKPSC JE Notification for 2025 will be out soon!
-> The total number of vacancies along with application dates will be mentioned in the notification.
-> The exam will be conducted to recruit Junior Engineers through Uttarakhand Public Service Commission.
-> Candidates with an engineering diploma in the concerned field are eligible.
-> The selection process includes a written exam and document verification. Prepare for the exam with UKPSC JE Previous Year Papers.