The technique which is activity oriented is : 

This question was previously asked in
UKPSC JE Civil 8 May 2022 Official Paper-I
View all UKPSC JE Papers >
  1. PERT
  2. LCES
  3. CPM
  4. Both 1 and 3

Answer (Detailed Solution Below)

Option 3 : CPM
Free
UKPSC JE CE Full Test 1 (Paper I)
180 Qs. 360 Marks 180 Mins

Detailed Solution

Download Solution PDF

Concept:

PERT stands for "Project Evaluation and Review Technique"

CPM stand for "Critical Path Method"

Difference between PERT and CPM:

PERT

CPM

 1. Probabilistic approach

 1. Deterministic approach

 2. Three-time estimate

 2. One-time estimate

 3. Event-oriented network   model

 3. Activity-oriented network
 model

 4. The slack concept is used

 4. Float concept is used

 5. Project crashing is not possible

 5. Project crashing is possible

 6. Deals with probabilistic time estimates

 6. Deals with deterministic time   estimates

Latest UKPSC JE Updates

Last updated on Mar 26, 2025

-> UKPSC JE Notification for 2025 will be out soon!

-> The total number of vacancies along with application dates will be mentioned in the notification.

-> The exam will be conducted to recruit Junior Engineers through Uttarakhand Public Service Commission. 

-> Candidates with an engineering diploma in the concerned field are eligible. 

-> The selection process includes a written exam and document verification. Prepare for the exam with UKPSC JE Previous Year Papers.

Hot Links: teen patti 50 bonus teen patti real cash teen patti lotus real cash teen patti