Comprehension

Consider the following PERT network: The optimistic time, most likely time and pessimistic time of all the activities are given in the table below:

GATE ME 2009 Images-Q55,56

Activity

 

Optimistic

time (days)

Most likely

time (days)

Pessimistic

time (days)

1 – 2

1

2

3

1 – 3

5

6

7

1 – 4

3

5

7

2 – 5

5

7

9

3 – 5

2

4

6

5 – 6

4

5

6

4 – 7

4

6

8

6 – 7

2

3

4

The critical path duration of the network (in days) is

This question was previously asked in
GATE ME 2009 Official Paper
View all GATE ME Papers >
  1. 11
  2. 14
  3. 17
  4. 18

Answer (Detailed Solution Below)

Option 4 : 18
Free
GATE ME 2023: Full Mock Test
5.7 K Users
65 Questions 100 Marks 180 Mins

Detailed Solution

Download Solution PDF

GATE ME 2009 Images-Q55

Activity

Optimistic time (T0)

Most likely Time(Tm)

Ppessimistic

Time (TP)

\({T_e} - {t_0} + 4{t_m} + {t_p}\)

expected

completion

 time (Te)

Variance

\({\sigma ^2} = {\left( {\frac{{{t_p} - {t_o}}}{6}} \right)^2}\)

1 – 2

1

2

3

\(\frac{{1 + 8 + 3}}{6} = 2\)

\({\left( {\frac{{3 - 1}}{6}} \right)^2} = \frac{1}{9}\)

1 – 3

5

6

7

\(\frac{{5 + 24 + 7}}{6} = 6\)

\({\left( {\frac{{7 - 5}}{6}} \right)^2} = \frac{1}{9}\)

1 – 4

3

5

7

\(\frac{{3 + 20 + 7}}{6} = 5\)

\({\left( {\frac{{7 - 3}}{6}} \right)^2} = \frac{4}{9}\)

2 – 5

5

7

9

\(\frac{{5 + 28 + 9}}{6} = 7\)

\({\left( {\frac{{9 - 5}}{6}} \right)^2} = \frac{4}{9}\)

3 – 5

2

4

6

\(\frac{{2 + 16 + 6}}{6} = 4\)

\({\left( {\frac{{6 - 2}}{6}} \right)^2} = \frac{4}{9}\)

5 – 6

4

5

6

\(\frac{{4 + 20 + 6}}{6} = 5\)

\({\left( {\frac{{6 - 4}}{6}} \right)^2} = \frac{1}{9}\)

4 – 7

4

6

8

\(\frac{{4 + 24 + 8}}{6} = 6\)

\({\left( {\frac{{3 - 4}}{6}} \right)^2} = \frac{4}{9}\)

6 – 7

2

3

4

\(\frac{{2 + 12 + 4}}{6} = 3\)

\({\left( {\frac{{4 - 2}}{6}} \right)^2} = \frac{1}{9}\)

hence path 1 – 3 – 5 – 6 – 7  is the critical path, which has 18 days of expected completion time

Latest GATE ME Updates

Last updated on Feb 19, 2024

-> GATE ME Answer Key has been released. The exam was held on 3rd, 4th, 10th, and 11th February 2024.

-> The Graduate Aptitude Test in Engineering, also known as GATE, conducts an Entrance exam that serves as a gateway for all Engineering aspirants.

->  Candidates who want a successful selection can refer to the GATE ME Preparation Tips to boost their exam preparation and increase their chances of selection.

->  Candidates must attempt the GATE ME Mock tests

More Operations Research Questions

Get Free Access Now
Hot Links: teen patti rummy teen patti master 2023 all teen patti teen patti real