Critical path indicates which one of the following?

This question was previously asked in
UGC Paper 2: Commerce 22nd Dec 2018
View all UGC NET Papers >
  1. Longest route of completing a task

  2. Shortest route of completing a task

  3. Average time of completing a task

  4. Recorded time of completing a task 

Answer (Detailed Solution Below)

Option 1 :

Longest route of completing a task

Free
UGC NET Paper 1: Held on 21st August 2024 Shift 1
16.6 K Users
50 Questions 100 Marks 60 Mins

Detailed Solution

Download Solution PDF

A critical path is a sequence of interdependent activities or tasks that must be finished before the project can be finished. It is the longest path (i.e. path with the longest duration) from project start to finish.

quesImage56

A. Critical Path Method

  1. The critical path method (CPM) is a project modeling technique that’s used by project managers to find important deadlines and deliver a project on time.
  2. In a project, the critical path is the longest distance between the start and the finish, including all the tasks and their duration.
  3. Once a critical path is determined, you’ll have a clear picture of the project’s actual schedule.
  4. To find this, project managers use the CPM algorithm to find the least amount of time necessary to complete each task with the least amount of slack.
  5. Once done by hand, nowadays, the critical path is calculated automatically by the project scheduling software. That makes the whole method a whole lot easier.

B.Critical Path Analysis

  1. As mentioned, the purpose of a critical path is to find the least amount of time you’ll need to complete a task.
  2. Critical path analysis furthers your ability to make better estimates for scheduling because you’re mapping out every important task that must be done for a successful project.

C. Critical Path Example

Therefore, from the above explanation, the Critical path indicates the Longest route of completing a task.

Latest UGC NET Updates

Last updated on Jul 21, 2025

-> The UGC NET Final Answer Key 2025 June has been released by NTA on its official website.

-> The UGC NET June 2025 Result has been released on the official website ugcnet.nta.ac.in on 22nd July 2025.

-> The UGC NET June 2025 exam will be conducted from 25th to 29th June 2025.

-> The UGC NET exam takes place for 85 subjects, to determine the eligibility for 'Junior Research Fellowship’ and ‘Assistant Professor’ posts, as well as for PhD. admissions.

-> The exam is conducted bi-annually - in June and December cycles.

-> The exam comprises two papers - Paper I and Paper II. Paper I consists of 50 questions and Paper II consists of 100 questions. 

-> The candidates who are preparing for the exam can check the UGC NET Previous Year Papers and UGC NET Test Series to boost their preparations.

More Production Function Questions

Get Free Access Now
Hot Links: teen patti flush teen patti star login teen patti real cash 2024