Sequencing Question 1:
Number of jobs delayed according to earliest due date rule to sequence job is,
Job | Processing time (day) | Due Dtae |
1 | 8 |
8 |
2 | 3 | 17 |
3 | 4 | 25 |
4 | 7 | 21 |
5 | 5 | 19 |
Answer (Detailed Solution Below)
Option 2 :
2
Sequencing Question 1 Detailed Solution
∴ 4 and 3 are delayed
job |
time |
jft |
Due date |
1 |
8 |
8 |
8 |
2 |
3 |
11 |
17 |
5 |
5 |
16 |
19 |
4 |
7 |
23 |
21 |
3 |
4 |
27 |
25 |
|
|
|
|